State-owned Ltd on Tuesday said it will invest an estimated Rs 19,650 crore to strengthen its


The move will increase coal evacuation capacity of the PSU through rail mode by an additional 330 million tonnes per annum (MTPA) by FY2023-24 when the production is expected to scale up significantly.





The upcoming projects, some of which are already operational, would help CIL despatch increased volumes of coal through rail, above the existing capacity, from its greenfield and brownfield mining areas, (CIL) said in a statement.


The coal mining behemoth is constructing three important railway lines from its own funds, on deposit basis, in CCL and MCL at an estimated capital of Rs 7,994 crore having 170 MTPA coal transportation capacity.


Additionally, the company has forged four rail joint ventures with Chhattisgarh, Jharkhand and Odisha at a capital outlay of Rs 11,656 crore which would help move 160 MTPA of coal.


Central Coalfields Ltd (CCL), Mahanadi Coalfields Ltd (MCL) and South Eastern Coalfields Ltd (SECL) are subsidiaries of CIL.


“These rail infra projects would boost our evacuation. It is important to have a robust coal transport mechanism in place to cope up with increased volumes of production in the ensuing years. We are laying the groundwork for it,” the company said.


Around 69 per cent of CIL’s overall coal output is expected from CCL, MCL and SECL by FY’25 and it is in these fields that the company is aggressively laying foundation for evacuation infrastructure.


The doubling of Tori-Shivpur (CCL) rail line was already commissioned in December 2019 and the tripling of the line which is under process shall enhance evacuation capacity to 100 MTPA from the existing 32 MTPA.


Jharsuguda-Barpali-Sardega (MCL) single line was commissioned in April 2018 and the construction work for doubling of the line along with loading bulb at Barpali and a flyover complex at Jharsuguda are under progress.


Dovetailing of first-mile connectivity (FMC) projects of Sardega 20 MTPA and Lajkura 15 MTPA to this rail connectivity would lift MCL’s transportation capacity additionally by 65 MTPA.


The four rail JVs are in various stages of progress with the main rail corridor of Kharsia to Dharamjaigarh, a 74 KM stretch under CERL in SECL already operational. CIL holds 64 per cent stake in these JVs with the rest 36 per cent made up by the rail PSUs and respective states.


Currently, CIL’s rail transportation from its own sidings accounts for 56 per cent of its total supplies. If loading from goods sheds, private washeries and merry-go-round (MGR) is also considered then the percentage of rail movement of coal goes higher to 79 per cent.

(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

mail Dear Reader,

Business Standard has always strived hard to provide up-to-date information and commentary on developments that are of interest to you and have wider political and economic implications for the country and the world. Your encouragement and constant feedback on how to improve our offering have only made our resolve and commitment to these ideals stronger. Even during these difficult times arising out of Covid-19, we continue to remain committed to keeping you informed and updated with credible news, authoritative views and incisive commentary on topical issues of relevance.

We, however, have a request.

As we battle the economic impact of the pandemic, we need your support even more, so that we can continue to offer you more quality content. Our subscription model has seen an encouraging response from many of you, who have subscribed to our online content. More subscription to our online content can only help us achieve the goals of offering you even better and more relevant content. We believe in free, fair and credible journalism. Your support through more subscriptions can help us practise the journalism to which we are committed.

Support quality journalism and subscribe to Business Standard.

Digital Editor



[ad_2]

Source link